Projects

Pavement is our prime interest. We also complete our own demolition, land clearing, earthwork, underground utility installation and removal, excavation and trucking, joint seal, airfield lighting, and pavements recycling.

NASA

With the cancelation of the Shuttle Program, NASA had 15 individual sites that needed to be demolished to make way for future programs. Work included: complete building demos both metal and block, metal canopy demo, concrete and asphalt demo, landscaping demo, generator decommission, new concrete sidewalks, curbs and gutters, and asphalt, extensive electrical rework, new […]

Repair Brown rd., Twentynine Palms Marine Corps Base.

2 phases of construction were required for low impact of daily operations to office and training facilities. 3 roads were completely demolished and removed, and graded to NAVFAC specifications to also alleviate flood conditions. Extensive traffic control plans, scheduling and notification between contractor and customer was essential for a successful project. Approximately 5000 tons of […]

Edwards AFB, Plant 42 AFB and Ft Irwin, CA

Cutting Edge Concrete Services Inc. was awarded an IDIQ contract with multiple task orders consisting of repairing and renovating parking lots, roads, airfield shoulders, taxiways and main runways. Scope of work included; pulverized in place asphalt, redesign roadways, grading, import and export of material, compact subgrade and finish grade, demolition of existing concrete structures and […]

Zzyzx

Cutting Edge constructed a new 736 square foot 24 inch thick concrete foundation, with limited equipment access, on top of a hill to support three (3) 10,000 gallon HDPE Fire water storage tanks including appurtenances & accessories. Installed 220 L.F of 6” and 8” HDPE waterline piping delivery system supported by above ground pipe supports […]

Coso Junction

Safety edge was required on two (2) mile stretch of highway 395, from mile marker 20 through 22. Work included 5800 cubic yard of roadway excavation, 2200 tons of new asphalt in a specialty shoulder paver, removal of boulders in recovery zones, new corrugated drain pipes across the highway with flared ends and riprap, and […]

Pinto Basin Rd. – Joshua Tree National Park

Project Relevance: Re-Construction and repair of 10.47 miles of road. Asphalt pulverization, road survey, road grading, widening, realignment, compaction and testing. Placed over 28,890 tons of FHWA spec Super Pave asphalt, compaction and testing. Provided and assembled gabion and revetment matt’s. Demolish existing curb and provided new Colored curb, sidewalk, cross gutter and handicap ramps. […]

Military Aircraft Sunshades – Edwards AFB

Cutting Edge provided and installed ten 70’ wide x 80’ long x 35’ high aircraft sun shades, six on Ramp 8S and, 4 on Ramp 8N at the Edwards AFB F-35 complex. This was a design build project that required a complete concrete study for its strength and joint locations. The final design took this […]

NASA Project – Edwards AFB

Cutting Edge performed all demolition, electrical, grading and concrete placement and finishing operations for this project. Features include removing 14″ thick concrete and replacing it with 16″ reinforced 650 psi Flexural strength conc. The 2 areas were aircraft parking aprons and taxiways between buildings 4801 and 4826 located at NASA’s Neil Armstrong flight research. Formerly […]

Heritage Park Project- Riverbed Landscape After

Heritage Park Improvement Project

Heritage Park Improvements Project consisted of the installation of multiple custom shade structures throughout the base. The creation of a new recreation area at the Marine Corp Command office. Designing and installing new pull up bars and concrete pads at the Marine Corp physical training center. The design and installation of 15,000 square feet of new landscape that included […]

Cahuilla Tewanet Deck

This project consisted of the demolition and reconstruction of the existing decking and substructure of the Cahuilla Tewanet Overlook located within the San Bernardino National Forest. Due to the existing structural concerns, concrete footings were replaced although portions of the existing railings were protected and utilized for the reconstruction as well as historical markers and […]

Ventura Harbor

Approximately 90,000 Metric Ton of Armor Stone type rock has been quarried by Cutting Edge at 3 Corps of Engineers approved quarries; and transported to our lay-down area at Ventura Harbor California.  Cutting Edge then loads the rock aboard barges and transports it to the detached breakwater for placement by derrick crane.  This project has […]

Anacapa Stairs Project After Completion

Channel Islands National Park – Anacapa Island

The project entails the removal and replacement of an existing metal staircase on Anacapa Island. Anacapa Island is part of Channel Islands National Park and all necessary means will be taken to ensure its preservation and cleanliness. The mooring platform at Anacapa Cove has a thirty year old metal staircase that through the years of […]

F-22 Aircraft Parking Apron – Hickam AFB, Hawaii

Design-Bid-build of a new aircraft parking apron in support of the Hawaii Air National Guard (HIANG) F-22 fighter program. Project highlights include, Site and sub grade preparation to accommodate 22,000 square yards of Slip form concrete paving, New High mast lighting, Clear water rinse facility, Airfield edge lighting, relocation and upgrades to existing utilities. Challenges […]

AC Pavements Nebo/Yermo – MCLB Barstow, CA

This design build project was located at the Marine Corps Logistics Base, Barstow CA. Features of work included the demo of existing asphalt pavements and various concrete structures, extensive grading and compaction, import/export of materials, new curb and gutter, re adjustment of slip cans and valves, striping and slurry sealing of roadways. A total of […]

CDC Playgrounds – MCAGCC Twentynine Palms, CA

Cutting Edge Concrete Services, Inc provided numerous upgrades to the existing Child Development Center (CDC) which is located at the Marine Corps Ground Combat Center (MCAGCC), Twentynine Palms, CA. Upgrades included removing existing sand and playground equipment as well as providing ADA accessibility throughout the play areas of three different age groups. Cutting Edge installed […]

Buildings 192 & 193 – YMCA

Cutting Edge was contracted to perform the complete engineering to facilitate the removal and replacement of existing parking areas at buildings 192 and 193 YMCA location. This work also required the over excavation of the parking areas, placement of petromat to stabilize the subgrade and all required testing and QC elements. In addition, the project’s […]